    PracticePMI PMP®PMI PMP Practice Exam 6Question 07
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamimpediment removalservant leadershipproblem solvingagile

    PMP · Question 07 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    During a daily standup, the development team reports they cannot proceed with integration testing because the test environment is down and the infrastructure team estimates it will take 3 days to restore. This is blocking multiple user stories. What should the project manager do FIRST?

    Answer options:

    A.

    Update the project schedule to reflect the 3-day delay and inform stakeholders

    B.

    Work with the infrastructure team to explore alternatives such as using a backup environment or expediting the repair

    C.

    Have the development team work on other user stories while waiting for the environment

    D.

    Escalate the issue to senior management to prioritize the infrastructure repair

    How to approach this question

    Look for proactive approaches that actively work to remove impediments rather than accepting or working around them. Servant leaders remove blockers.

    Full Answer

    B.Work with the infrastructure team to explore alternatives such as using a backup environment or expediting the repair✓ Correct
    B
    Servant leaders actively work to remove impediments and blockers for their teams. This means exploring alternatives and solutions rather than simply accepting delays.

    Common mistakes

    Accepting impediments without exploring solutions, or immediately escalating without first working directly with the responsible parties.
    Question 06All questionsQuestion 08

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard