PMP · Question 03 · Task 3: Support team performance
A team member who was previously a high performer has shown declining work quality and missed several sprint commitments over the past two iterations. Other team members are starting to express frustration. What should the project manager do FIRST to support team performance?
Answer options:
Have a private one-on-one conversation with the team member to understand what might be affecting their performance
Reassign the team member's tasks to other team members to ensure sprint goals are met
Address the performance issues during the next team retrospective
Document the performance issues and escalate to the functional manager