Hard1 markMultiple Choice
Task 6: Plan and manage schedulePERTschedule managementthree-point estimationactivity duration

PMP · Question 20 · Task 6: Plan and manage schedule

A project manager is developing a schedule for a complex software project with multiple dependencies. The team has provided optimistic, pessimistic, and most likely estimates for key activities. Activity A has estimates of 5, 15, and 8 days respectively. What is the expected duration for Activity A using the PERT formula?

Answer options:

A.

8.0 days

B.

8.5 days

C.

9.3 days

D.

9.0 days

How to approach this question

Apply the PERT formula: (Optimistic + 4×Most Likely + Pessimistic) ÷ 6. Be careful with the calculation and rounding.

Full Answer

B.8.5 days✓ Correct
B
The PERT formula provides a weighted average that emphasizes the most likely estimate: (O + 4M + P) ÷ 6 = (5 + 32 + 15) ÷ 6 = 8.67 days.

Common mistakes

Using simple average instead of PERT formula, calculation errors, or incorrect weighting of the most likely estimate.