PMP · Question 20 · Task 6: Plan and manage schedule
A project manager is developing a schedule for a complex software project with multiple dependencies. The team has provided optimistic, pessimistic, and most likely estimates for key activities. Activity A has estimates of 5, 15, and 8 days respectively. What is the expected duration for Activity A using the PERT formula?
Answer options:
8.0 days
8.5 days
9.3 days
9.0 days