Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementSPIschedule performanceperformance measurement
PMP · Question 54 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $480,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only.
A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $480,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only.
How to approach this question
Calculate SPI using the formula: SPI = EV / PV. This indicates schedule performance relative to the plan.
Full Answer
Schedule Performance Index (SPI) = EV / PV = 400,000 / 480,000 = 0.833. An SPI less than 1.0 indicates the project is behind schedule.
Common mistakes
Using wrong formula (confusing with CPI), calculation errors, or incorrect rounding.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert