Hard1 markMultiple Choice
PMP · Question 55 · Task 6: Plan and manage schedule
A project manager is developing a schedule for a software project with the following activities on the critical path: Analysis (5 days), Design (8 days), Development (12 days), Testing (6 days), and Deployment (2 days). If Development can be started 3 days after Design begins (fast-tracking), what is the new critical path duration?
A project manager is developing a schedule for a software project with the following activities on the critical path: Analysis (5 days), Design (8 days), Development (12 days), Testing (6 days), and Deployment (2 days). If Development can be started 3 days after Design begins (fast-tracking), what is the new critical path duration?
Answer options:
A.
30 days
B.
28 days
C.
27 days
D.
25 days
How to approach this question
Calculate the overlap carefully: Development starts 3 days after Design begins, so there's a 3-day overlap that reduces the total duration.
Full Answer
C.27 days✓ Correct
C
With fast-tracking, Development starts 3 days into Design, creating overlap. Total duration = 5 + (8 + 12 - 3) + 6 + 2 = 27 days, saving 3 days from the original 30-day duration.
Common mistakes
Not accounting for the overlap correctly, adding the overlap instead of subtracting it, or miscalculating the parallel work duration.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert