Hard1 markMultiple Choice
Task 6: Plan and manage scheduleschedule managementfast-trackingcritical pathactivity overlap

PMP · Question 55 · Task 6: Plan and manage schedule

A project manager is developing a schedule for a software project with the following activities on the critical path: Analysis (5 days), Design (8 days), Development (12 days), Testing (6 days), and Deployment (2 days). If Development can be started 3 days after Design begins (fast-tracking), what is the new critical path duration?

Answer options:

A.

30 days

B.

28 days

C.

27 days

D.

25 days

How to approach this question

Calculate the overlap carefully: Development starts 3 days after Design begins, so there's a 3-day overlap that reduces the total duration.

Full Answer

C.27 days✓ Correct
C
With fast-tracking, Development starts 3 days into Design, creating overlap. Total duration = 5 + (8 + 12 - 3) + 6 + 2 = 27 days, saving 3 days from the original 30-day duration.

Common mistakes

Not accounting for the overlap correctly, adding the overlap instead of subtracting it, or miscalculating the parallel work duration.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam