Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementSPI calculationschedule performanceproject metrics

PMP · Question 56 · Task 5: Plan and manage budget and resources

A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $500,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)

How to approach this question

Calculate SPI using the formula: SPI = EV / PV. Round to two decimal places and enter numbers only.

Full Answer

0.80
SPI = EV / PV = 400,000 / 500,000 = 0.80. An SPI less than 1.0 indicates the project is behind schedule.

Common mistakes

Students often confuse SPI with CPI (EV/AC) or calculate incorrectly by using AC instead of PV in the denominator.

Practice the full PMI PMP Practice Exam 5

94 questions · hints · full answers · grading

More questions from this exam