Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementSPI calculationschedule performanceproject metrics
PMP · Question 56 · Task 5: Plan and manage budget and resources
A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $500,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)
A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completion (BAC): $800,000<br/>- Planned Value (PV): $500,000<br/>- Earned Value (EV): $400,000<br/>- Actual Cost (AC): $450,000<br/><br/>What is the Schedule Performance Index (SPI)? (Round to two decimal places, enter numbers only)
How to approach this question
Calculate SPI using the formula: SPI = EV / PV. Round to two decimal places and enter numbers only.
Full Answer
0.80
SPI = EV / PV = 400,000 / 500,000 = 0.80. An SPI less than 1.0 indicates the project is behind schedule.
Common mistakes
Students often confuse SPI with CPI (EV/AC) or calculate incorrectly by using AC instead of PV in the denominator.
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
Expert