For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 57
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleproject schedulingconstraint managementresource planningschedule development

    PMP · Question 57 · Task 6: Plan and manage schedule

    A project manager is developing a project schedule for a software development project with the following constraints: the development team is only available part-time, there are dependencies on external vendor deliverables, and the client has requested specific milestone dates for stakeholder reviews. What should the project manager do FIRST when creating the schedule?

    Answer options:

    A.

    Identify and document all project constraints, dependencies, and resource availability before developing the schedule

    B.

    Create an initial schedule based on ideal conditions and then adjust for constraints

    C.

    Focus on meeting the client's requested milestone dates and work backward from those dates

    D.

    Negotiate with stakeholders to remove or reduce the project constraints

    How to approach this question

    When developing schedules with multiple constraints, identify and document all limitations first to create realistic schedules rather than starting with ideal scenarios.

    Full Answer

    A.Identify and document all project constraints, dependencies, and resource availability before developing the schedule✓ Correct
    A
    Effective schedule development requires understanding all constraints, dependencies, and resource limitations first. This enables creation of realistic schedules that can actually be achieved.

    Common mistakes

    Students often choose ideal-condition scheduling (B) or milestone-driven approaches (C), missing the need to understand constraints before schedule development.
    Question 56All questionsQuestion 58

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →