    Hard1 markMultiple Choice
    Task 7: Plan and manage quality of products/deliverablesquality managementroot cause analysisregulatory complianceprocess improvement

    PMP · Question 58 · Task 7: Plan and manage quality of products/deliverables

    A project manager is implementing quality management for a medical device development project that must meet FDA regulatory standards. The project team has established quality processes, but recent testing has revealed several defects that could impact regulatory approval. The defects are not critical safety issues but do affect product performance. What should the project manager do FIRST?

    Answer options:

    A.

    Continue with the current quality processes since the defects are not safety-critical

    B.

    Analyze the root causes of the defects to determine if quality process improvements are needed

    C.

    Increase testing frequency to catch defects earlier in the development process

    D.

    Report the defects to the FDA as part of the regulatory compliance process

    How to approach this question

    When quality issues arise in regulated environments, analyze root causes to determine if systemic process improvements are needed rather than just managing symptoms.

    Full Answer

    B.Analyze the root causes of the defects to determine if quality process improvements are needed✓ Correct
    Quality management in regulated environments requires understanding why defects occur to improve processes and prevent future issues, not just detecting and managing defects after they occur.

    Common mistakes

    Students often choose increased testing (C) or regulatory reporting (D), missing the need for root cause analysis to improve quality processes.
    Question 57All questionsQuestion 59

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →