    Hard1 markMultiple Choice
    Task 8: Plan and manage scopescope managementrequirements prioritizationstakeholder collaborationbusiness value

    PMP · Question 59 · Task 8: Plan and manage scope

    A project manager is working with stakeholders to define project scope for a new customer portal. The marketing team wants extensive personalization features, the IT team wants to minimize complexity, and the customer service team wants comprehensive reporting capabilities. Each group has valid business justifications for their requirements. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate a requirements prioritization workshop to evaluate business value and implementation complexity of each requirement

    B.

    Include all requirements in the project scope to satisfy all stakeholder groups

    C.

    Ask the sponsor to decide which stakeholder group's requirements take priority

    D.

    Implement the requirements in phases based on stakeholder group seniority

    How to approach this question

    When stakeholders have competing scope requirements, facilitate collaborative prioritization based on business value and implementation factors rather than including everything or having others decide.

    Full Answer

    A.Facilitate a requirements prioritization workshop to evaluate business value and implementation complexity of each requirement✓ Correct
    A
    Requirements prioritization workshops enable stakeholders to collaboratively evaluate business value versus implementation complexity, leading to informed scope decisions that balance competing needs.

    Common mistakes

    Students often choose including all requirements (B) or sponsor decision-making (C), missing the opportunity for collaborative stakeholder prioritization.
    Question 58All questionsQuestion 60

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →