PMP · Question 60 · Task 9: Integrate project planning activities
A project manager is integrating plans from multiple workstreams for a large organizational transformation project. During integration analysis, they discover that the training plan assumes all system changes will be completed before training begins, but the system implementation plan shows a phased rollout over six months. This creates a significant integration gap. What should the project manager do FIRST?
A project manager is integrating plans from multiple workstreams for a large organizational transformation project. During integration analysis, they discover that the training plan assumes all system changes will be completed before training begins, but the system implementation plan shows a phased rollout over six months. This creates a significant integration gap. What should the project manager do FIRST?
Answer options:
Modify the training plan to align with the phased system implementation approach
Analyze all workstream dependencies to understand the full impact of the integration gap on project objectives
Change the system implementation to complete all changes before training begins
Schedule a meeting with both workstream leads to negotiate a compromise solution
How to approach this question
Full Answer
Common mistakes