    PracticePMI PMP®PMI PMP Practice Exam 5Question 61
    Hard1 markMultiple Choice
    Task 10: Manage project changeschange managementimpact assessmentchange controlvendor management

    PMP · Question 61 · Task 10: Manage project changes

    During project execution, a major client requests a significant scope addition that would add substantial value but also increase the project timeline by 8 weeks and budget by 25%. The client is willing to accept the timeline and budget increases. However, the change would require renegotiating contracts with two key vendors. What should the project manager do FIRST?

    Answer options:

    A.

    Accept the change since the client is willing to pay for the additional scope and timeline

    B.

    Begin renegotiating vendor contracts to understand the feasibility of the change

    C.

    Conduct a comprehensive impact assessment including vendor contract implications and submit to change control board

    D.

    Negotiate with the client to implement the change in a future project phase

    How to approach this question

    For significant change requests, conduct comprehensive impact assessment including all implications before making decisions, even when clients are willing to accept costs.

    Full Answer

    C.Conduct a comprehensive impact assessment including vendor contract implications and submit to change control board✓ Correct
    C
    Change management requires comprehensive impact assessment including vendor, resource, risk, and other implications before making decisions, regardless of client willingness to accept costs.

    Common mistakes

    Students often choose immediate acceptance (A) based on client willingness to pay, or contract negotiation (B), missing the need for comprehensive impact assessment first.
    Question 60All questionsQuestion 62

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →