PMP · Question 71 · Task 3: Evaluate and address external business environment changes for impact on scope
A project manager is leading a software development project when new data privacy regulations are announced that will take effect in eight months. The regulations will require significant changes to data handling processes, and the project's current scope includes features that may not comply with the new requirements. The project is scheduled to complete in six months. What should the project manager do FIRST?
A project manager is leading a software development project when new data privacy regulations are announced that will take effect in eight months. The regulations will require significant changes to data handling processes, and the project's current scope includes features that may not comply with the new requirements. The project is scheduled to complete in six months. What should the project manager do FIRST?
Answer options:
Analyze the new regulations to assess their specific impact on current project scope and deliverables
Accelerate the project timeline to complete delivery before the regulations take effect
Extend the project timeline to allow for compliance with the new regulations
Request legal counsel review of the new regulations and their project implications