    PracticePMI PMP®PMI PMP Practice Exam 5Question 63
    Hard1 markMultiple Choice
    Task 12: Manage project artifactsartifact managementdocument controlversion controlprocess improvement

    PMP · Question 63 · Task 12: Manage project artifacts

    A project manager discovers that important project documents are stored in multiple locations with inconsistent version control. Team members have been working with outdated requirements documents, and there have been several instances of decisions being made based on superseded information. This is causing rework and confusion. What should the project manager do FIRST?

    Answer options:

    A.

    Implement a centralized document management system immediately

    B.

    Assess current document management practices and stakeholder needs to develop a comprehensive artifact management solution

    C.

    Assign a team member to consolidate all documents and maintain version control going forward

    D.

    Send a communication to all team members about the importance of using current document versions

    How to approach this question

    When artifact management issues cause project problems, assess current practices and needs to develop systematic solutions rather than implementing quick fixes.

    Full Answer

    B.Assess current document management practices and stakeholder needs to develop a comprehensive artifact management solution✓ Correct
    B
    Effective artifact management requires understanding current practices, identifying root causes of problems, and understanding stakeholder needs before implementing management solutions.

    Common mistakes

    Students often choose immediate system implementation (A) or administrative solutions (C), missing the need for systematic assessment to understand and address root causes.
    Question 62All questionsQuestion 64

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →