PMP · Question 82 · Task 10: Build shared understanding
During a project planning session, different stakeholders express conflicting interpretations of a key project deliverable. The technical team understands it as a data integration platform, the business team expects a complete analytics solution, and the end users anticipate a self-service reporting tool. What should the project manager do FIRST?
During a project planning session, different stakeholders express conflicting interpretations of a key project deliverable. The technical team understands it as a data integration platform, the business team expects a complete analytics solution, and the end users anticipate a self-service reporting tool. What should the project manager do FIRST?
Answer options:
Update the project charter to provide clearer deliverable definitions
Ask the sponsor to clarify which interpretation is correct for the project
Facilitate a requirements clarification session with all stakeholders to reach consensus on the deliverable
Proceed with the technical team's interpretation since they will be implementing the solution
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert