PMP · Question 14 · Task 10: Build shared understanding
A project manager discovers that stakeholders have different interpretations of a key project deliverable. The business stakeholders expect a fully automated solution, while the technical team understood it as a semi-automated system with manual oversight. This misunderstanding wasn't discovered until the design review phase. What should the project manager do FIRST?
A project manager discovers that stakeholders have different interpretations of a key project deliverable. The business stakeholders expect a fully automated solution, while the technical team understood it as a semi-automated system with manual oversight. This misunderstanding wasn't discovered until the design review phase. What should the project manager do FIRST?
Answer options:
Update the project requirements document to clarify the deliverable specifications
Facilitate a requirements clarification session with all stakeholders to reach consensus
Ask the sponsor to make the final decision on which interpretation is correct
Continue with the technical team's interpretation since development has already begun
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert