For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 34
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceregulatory complianceHIPAAvendor compliancecompliance assessment

    PMP · Question 34 · Task 1: Plan and manage project compliance

    A healthcare project must comply with HIPAA regulations for patient data protection. During a security audit, the project manager discovers that a third-party vendor's data handling practices may not fully comply with HIPAA requirements, even though they claim to be compliant. The vendor is critical to project success and replacing them would cause significant delays. What should the project manager do FIRST?

    Answer options:

    A.

    Continue working with the vendor while implementing additional security measures

    B.

    Conduct a detailed compliance assessment of the vendor's practices with legal and security teams

    C.

    Immediately terminate the vendor relationship to avoid compliance risks

    D.

    Request written certification from the vendor that they are fully HIPAA compliant

    How to approach this question

    When compliance issues are discovered, conduct thorough assessment with appropriate expertise before making decisions about how to proceed.

    Full Answer

    B.Conduct a detailed compliance assessment of the vendor's practices with legal and security teams✓ Correct
    B
    Regulatory compliance issues require thorough assessment with appropriate legal and technical expertise to understand actual compliance status and determine appropriate corrective actions.

    Common mistakes

    Students often choose immediate termination (C) to avoid risk, or continuation with measures (A), missing the need for proper compliance assessment first.
    Question 33All questionsQuestion 35

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →