PMP · Question 31 · Task 15: Manage project issues
During project execution, a risk that was identified in the risk register has materialized into an actual issue: a key team member has left the organization unexpectedly, and their specialized knowledge is critical for the upcoming deliverable. The team is struggling to maintain progress without this expertise. What should the project manager do FIRST?
During project execution, a risk that was identified in the risk register has materialized into an actual issue: a key team member has left the organization unexpectedly, and their specialized knowledge is critical for the upcoming deliverable. The team is struggling to maintain progress without this expertise. What should the project manager do FIRST?
Answer options:
Update the risk register to reflect that the risk has become an issue
Begin recruiting a replacement team member with similar specialized knowledge
Collaborate with the team and stakeholders to identify immediate solutions for maintaining deliverable progress
Escalate the staffing issue to HR and senior management for resolution
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert