For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 73
    Hard1 markMultiple Choice
    Task 1: Manage conflictconflict resolutiontechnical conflictsproblem solvingcollaboration

    PMP · Question 73 · Task 1: Manage conflict

    A project manager is leading a team where two experienced developers have different approaches to solving a critical technical problem. One developer advocates for a proven, conservative solution, while the other proposes an innovative but untested approach. The disagreement is creating tension and affecting team productivity. Which TWO conflict resolution approaches should the project manager use FIRST?

    Answer options:

    A.

    Problem-solving - Focus on understanding the underlying technical requirements and constraints to find the best solution

    B.

    Compromising - Find a middle ground that incorporates elements of both technical approaches

    C.

    Forcing - Make a decision as project manager to resolve the technical conflict quickly

    D.

    Collaborating - Work together to evaluate both approaches against project objectives and find the best solution

    E.

    Avoiding - Allow the developers to work out the technical disagreement independently

    F.

    Smoothing - Emphasize the technical expertise of both developers and minimize the importance of the differences

    How to approach this question

    For technical conflicts between experienced team members, use approaches that leverage expertise and focus on objective evaluation rather than quick resolution or avoidance.

    Full Answer

    A,D
    Problem-solving and collaboration are complementary techniques that focus on objective evaluation of technical merits and leverage team expertise to find the best solution.

    Common mistakes

    Students often choose compromising (B) thinking it's collaborative, or forcing (C) for quick resolution, missing the need for objective technical evaluation through problem-solving and collaboration.
    Question 72All questionsQuestion 74

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →