PMP · Question 17 · Task 1: Execute project with the urgency required to deliver business value
A project manager needs to assess opportunities to deliver value incrementally in a large enterprise software implementation. The traditional approach would deliver the entire system after 18 months, but stakeholders are concerned about the long wait for business benefits. What should the project manager do FIRST to identify incremental value delivery opportunities?
Answer options:
Analyze the business processes and identify which modules can deliver standalone value
Divide the 18-month timeline into six 3-month phases for regular delivery milestones
Implement an agile methodology to enable iterative development and delivery
Survey stakeholders to determine their preferred delivery schedule and priorities