PMP · Question 53 · Task 2: Manage communications
A project manager is developing a communication strategy for a regulatory compliance project involving multiple government agencies, internal legal teams, executive leadership, and operational staff. Each stakeholder group has different information needs, decision-making timelines, and communication preferences. Which TWO factors should the project manager prioritize when designing the communication approach?
A project manager is developing a communication strategy for a regulatory compliance project involving multiple government agencies, internal legal teams, executive leadership, and operational staff. Each stakeholder group has different information needs, decision-making timelines, and communication preferences. Which TWO factors should the project manager prioritize when designing the communication approach?
Answer options:
The project manager's expertise with different communication tools and methods
The decision-making processes and timelines of each stakeholder group
The organizational hierarchy and reporting relationships between stakeholder groups
The specific information requirements and level of detail needed by each audience
The cost and resource requirements for different communication methods
The geographic distribution and time zones of stakeholder groups
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert