Hard1 markMultiple Choice
Task 16: Ensure knowledge transfer for project continuityknowledge transfersystem transitionreadiness assessmentoperations handover

PMP · Question 67 · Task 16: Ensure knowledge transfer for project continuity

A project manager is preparing for a transition where the project team will hand over a new financial system to the operations team. The operations team has expressed concerns about their readiness to support the complex system, and some project team members have unique knowledge that won't be easily replaced. The transition is scheduled to occur in six weeks. What should the project manager do FIRST?

Answer options:

A.

Conduct a comprehensive readiness assessment to identify specific knowledge transfer and capability gaps

B.

Schedule intensive training sessions for the operations team on all system functions

C.

Create detailed documentation of all system processes and procedures

D.

Extend the transition timeline to allow more time for knowledge transfer

How to approach this question

When planning complex system transitions, conduct comprehensive readiness assessment first to understand specific knowledge transfer and capability needs.

Full Answer

A.Conduct a comprehensive readiness assessment to identify specific knowledge transfer and capability gaps✓ Correct
A
Effective knowledge transfer for complex systems requires understanding the receiving team's current capabilities and specific knowledge needs to develop appropriate transfer strategies.

Common mistakes

Students often choose immediate training (B) or documentation (C), missing the need for readiness assessment to understand specific knowledge transfer requirements.

Practice the full PMI PMP Practice Exam 5