PMP · Question 10 · Task 13: Determine appropriate project methodology/methods and practices
A construction company is building a hospital with strict regulatory requirements, detailed architectural plans, and a fixed completion date for the opening. However, the medical equipment selection and interior design can evolve based on staff feedback during construction. Which project approach would be MOST appropriate for this scenario?
Answer options:
Predictive approach - The regulatory requirements and fixed date require traditional planning
Agile approach - The evolving requirements for equipment and design need iterative delivery
Hybrid approach - Predictive for construction with agile elements for equipment/design decisions
Iterative approach - Multiple cycles allow for continuous refinement of all aspects
94 questions · hints · full answers · grading