    PracticePMI PMP®PMI PMP Practice Exam 5Question 46
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder collaborationcompeting prioritiesstakeholder alignmentbusiness objectives

    PMP · Question 46 · Task 9: Collaborate with stakeholders

    A project manager is working with multiple stakeholder groups who have different priorities and expectations for the project outcomes. The marketing team wants features that enhance customer experience, the operations team wants features that reduce maintenance overhead, and the finance team wants to minimize development costs. These competing priorities are creating tension in stakeholder meetings. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate a collaborative session to understand each group's underlying business objectives and find alignment opportunities

    B.

    Ask the sponsor to prioritize the competing stakeholder requirements

    C.

    Develop separate project phases to address each stakeholder group's priorities sequentially

    D.

    Create a stakeholder communication plan to manage expectations about competing priorities

    How to approach this question

    When stakeholders have competing priorities, facilitate collaborative understanding of underlying objectives to find alignment opportunities rather than having others decide or managing around the conflicts.

    Full Answer

    A.Facilitate a collaborative session to understand each group's underlying business objectives and find alignment opportunities✓ Correct
    Stakeholder collaboration requires understanding underlying business objectives rather than just stated requirements. This often reveals alignment opportunities and enables more effective priority setting.

    Common mistakes

    Students often choose sponsor decision-making (B) or process solutions (C or D), missing the opportunity for collaborative stakeholder alignment around business objectives.
    Question 45All questionsQuestion 47

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →