    PracticePMI PMP®PMI PMP Practice Exam 5Question 91
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valuebenefits realizationERP implementationroot cause analysisbusiness value

    PMP · Question 91 · Task 2: Evaluate and deliver project benefits and value

    A project manager is evaluating the benefits realization of an enterprise resource planning (ERP) system implementation nine months after go-live. The system has achieved technical performance targets, but business benefits show mixed results: inventory management improved by 25% (target: 20%), but order processing time improved by only 5% (target: 15%). What should the project manager do FIRST?

    Answer options:

    A.

    Report the mixed results to stakeholders and recommend system configuration changes to improve order processing

    B.

    Investigate the factors contributing to the gap between expected and actual order processing improvements

    C.

    Adjust the order processing target to reflect the system's actual performance capabilities

    D.

    Extend the benefits measurement period since ERP implementations often take longer to show full benefits

    How to approach this question

    When benefits realization shows mixed results, investigate root causes of underperformance before reporting results or making adjustments to understand corrective actions needed.

    Full Answer

    B.Investigate the factors contributing to the gap between expected and actual order processing improvements✓ Correct
    B
    Benefits realization management requires investigating root causes when actual benefits fall short of expectations, enabling development of corrective actions to achieve intended business value.

    Common mistakes

    Students often choose immediate reporting (A) or target adjustment (C), missing the need for root cause investigation to understand and address benefit realization gaps.
    Question 90All questionsQuestion 92

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →