For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 114
    Medium1 markMultiple Choice
    Task 7: Plan and manage qualityProcessAgileQuality

    PMP · Question 114 · Task 7: Plan and manage quality

    A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'Definition of Done' (DoD). What is this?

    Answer options:

    A.

    When the developer says it works.

    B.

    A shared checklist of criteria that must be met for a backlog item to be considered complete (e.g., coded, tested, documented).

    C.

    The acceptance criteria for a specific story.

    D.

    The project end date.

    How to approach this question

    DoD = Quality Checklist for Everything.

    Full Answer

    B.A shared checklist of criteria that must be met for a backlog item to be considered complete (e.g., coded, tested, documented).✓ Correct
    Task 7 (Quality) and Task 10 (Shared Understanding). DoD ensures quality and prevents technical debt.

    Common mistakes

    Confusing DoD (Global) with Acceptance Criteria (Local/Story specific).
    Question 113All questions

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →