Medium1 markMultiple Choice
PMP · Question 114 · Task 7: Plan and manage quality
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'Definition of Done' (DoD). What is this?
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'Definition of Done' (DoD). What is this?
Answer options:
A.
When the developer says it works.
B.
A shared checklist of criteria that must be met for a backlog item to be considered complete (e.g., coded, tested, documented).
C.
The acceptance criteria for a specific story.
D.
The project end date.
How to approach this question
DoD = Quality Checklist for Everything.
Full Answer
B.A shared checklist of criteria that must be met for a backlog item to be considered complete (e.g., coded, tested, documented).✓ Correct
B
Task 7 (Quality) and Task 10 (Shared Understanding). DoD ensures quality and prevents technical debt.
Common mistakes
Confusing DoD (Global) with Acceptance Criteria (Local/Story specific).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert