PMP · Question 72 · Task 11: Plan and manage procurement
A project manager is leading a project with a fixed price contract. The seller claims that a specific requirement was not in the original scope and asks for a change order. The PM disagrees. What should the PM do FIRST?
Answer options:
Refuse to pay.
Review the contract, SOW, and WBS dictionary to verify the scope definition.
Agree to the change to maintain the relationship.
Enter Alternative Dispute Resolution (ADR).
114 questions · hints · full answers · grading