    PracticePMI PMP®PMI PMP Practice ExamQuestion 72
    Hard1 markMultiple Choice
    Task 11: Plan and manage procurementProcessProcurementScope

    PMP · Question 72 · Task 11: Plan and manage procurement

    A project manager is leading a project with a fixed price contract. The seller claims that a specific requirement was not in the original scope and asks for a change order. The PM disagrees. What should the PM do FIRST?

    Answer options:

    A.

    Refuse to pay.

    B.

    Review the contract, SOW, and WBS dictionary to verify the scope definition.

    C.

    Agree to the change to maintain the relationship.

    D.

    Enter Alternative Dispute Resolution (ADR).

    How to approach this question

    Dispute -> Check Documents.

    Full Answer

    B.Review the contract, SOW, and WBS dictionary to verify the scope definition.✓ Correct
    B
    Task 11 (Procurement) and Task 8 (Scope). Disputes often arise from ambiguity. The first step is to check the contract documents.

    Common mistakes

    Jumping to conflict (A) or capitulation (C) without reading the contract.
    Question 71All questionsQuestion 73

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →