    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 14
    Hard1 markMultiple Choice
    Task 14: Promote team performance through EIPeopleEmotional IntelligencePerformance

    PMP · Question 14 · Task 14: Promote team performance through EI

    A project manager notices that a usually reliable team member is making errors. The PM knows the team member is going through a divorce. Which TWO actions demonstrate the application of emotional intelligence?

    Answer options:

    A.

    Ignore the personal situation and focus strictly on the data of the errors.

    B.

    Tell the team member they need to leave their personal problems at home.

    C.

    Privately acknowledge the difficulty the team member is facing (empathy).

    D.

    Offer temporary flexibility in working hours or workload to reduce stress.

    E.

    Announce to the team that the member is struggling so they can help.

    How to approach this question

    Choose options that balance empathy with performance support.

    Full Answer

    C,D
    EI involves recognizing emotions and managing relationships. Acknowledging the struggle and offering flexibility builds loyalty and helps the member recover performance.

    Common mistakes

    Thinking 'professionalism' means ignoring personal context (A, B).
    Question 13All questionsQuestion 15

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
    View all 20 questions →