PMP · Question 16 · Task 5: Ensure team members/stakeholders are adequately trained
A project manager is leading a team that includes several junior developers who are new to agile practices. During sprint planning, these team members consistently underestimate their tasks, leading to incomplete sprints. What should the project manager do to address this situation?
A project manager is leading a team that includes several junior developers who are new to agile practices. During sprint planning, these team members consistently underestimate their tasks, leading to incomplete sprints. What should the project manager do to address this situation?
Answer options:
Assign a senior developer to review and adjust all estimates made by junior team members
Facilitate estimation sessions where junior and senior developers collaborate to share knowledge and improve estimation accuracy
Reduce the sprint capacity to account for the estimation inaccuracy
Require junior developers to complete estimation training before participating in sprint planning
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
Expert