Hard1 markMultiple Choice
Task 1: Plan and manage project compliancesecurity compliancegovernment contractsteam managementcompliance requirements
PMP · Question 19 · Task 1: Plan and manage project compliance
A project manager is working on a government contract that requires specific security clearances for all team members. During project execution, a key team member's security clearance is revoked due to personal issues. What should the project manager do FIRST?
A project manager is working on a government contract that requires specific security clearances for all team members. During project execution, a key team member's security clearance is revoked due to personal issues. What should the project manager do FIRST?
Answer options:
A.
Continue using the team member on non-sensitive tasks while seeking clearance reinstatement
B.
Immediately remove the team member from the project and assess the impact on project deliverables
C.
Negotiate with the client to allow the team member to continue working under supervision
D.
Document the situation and continue with the current work while seeking guidance
How to approach this question
In compliance scenarios, especially with security requirements, immediate adherence to requirements takes priority over project convenience or team member considerations.
Full Answer
B.Immediately remove the team member from the project and assess the impact on project deliverables✓ Correct
B
Government contracts with security requirements have strict compliance mandates. Immediate removal prevents contract violations while impact assessment guides next steps.
Common mistakes
Trying to find workarounds for security requirements or continuing work while seeking guidance, which could violate contract terms.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert