Hard1 markMultiple Choice
Task 8: Negotiate project agreementsnegotiationvendor managementcollaborative problem solvingcost management

PMP · Question 21 · Task 8: Negotiate project agreements

A project manager is negotiating a contract with a vendor for critical project components. The vendor is demanding a 20% price increase due to raw material cost escalations, but the project budget cannot accommodate this increase. What should the project manager do FIRST?

Answer options:

A.

Explore alternative solutions such as specification changes, different materials, or phased delivery to reduce costs

B.

Reject the price increase and seek alternative vendors immediately

C.

Accept the price increase and request additional budget from the sponsor

D.

Demand that the vendor honor the original price as per the initial agreement

How to approach this question

Look for collaborative approaches that seek win-win solutions by exploring alternatives rather than taking adversarial positions.

Full Answer

A.Explore alternative solutions such as specification changes, different materials, or phased delivery to reduce costs✓ Correct
Effective negotiation seeks win-win solutions by exploring alternatives that address underlying needs rather than fixed positions.

Common mistakes

Taking adversarial positions or immediately accepting/rejecting proposals without exploring creative alternatives that could benefit both parties.

Practice the full PMI PMP Practice Exam 3

100 questions · hints · full answers · grading

More questions from this exam