Hard1 markMultiple Choice
Task 8: Negotiate project agreementsnegotiationvendor managementcollaborative problem solvingcost management
PMP · Question 21 · Task 8: Negotiate project agreements
A project manager is negotiating a contract with a vendor for critical project components. The vendor is demanding a 20% price increase due to raw material cost escalations, but the project budget cannot accommodate this increase. What should the project manager do FIRST?
A project manager is negotiating a contract with a vendor for critical project components. The vendor is demanding a 20% price increase due to raw material cost escalations, but the project budget cannot accommodate this increase. What should the project manager do FIRST?
Answer options:
A.
Explore alternative solutions such as specification changes, different materials, or phased delivery to reduce costs
B.
Reject the price increase and seek alternative vendors immediately
C.
Accept the price increase and request additional budget from the sponsor
D.
Demand that the vendor honor the original price as per the initial agreement
How to approach this question
Look for collaborative approaches that seek win-win solutions by exploring alternatives rather than taking adversarial positions.
Full Answer
A.Explore alternative solutions such as specification changes, different materials, or phased delivery to reduce costs✓ Correct
Effective negotiation seeks win-win solutions by exploring alternatives that address underlying needs rather than fixed positions.
Common mistakes
Taking adversarial positions or immediately accepting/rejecting proposals without exploring creative alternatives that could benefit both parties.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert