    PracticePMI PMP®PMI PMP Practice Exam 3Question 28
    Hard1 markMultiple Choice
    Task 2: Evaluate and deliver project benefits and valuevalue deliveryuser feedbackbacklog managementstakeholder engagement

    PMP · Question 28 · Task 2: Evaluate and deliver project benefits and value

    A project manager is evaluating the business value delivery of an agile project at the end of the third iteration. The team has delivered all planned features, but user feedback indicates that while the features work correctly, they don't significantly improve the user experience. Which TWO actions should the project manager take?

    Answer options:

    A.

    Work with the product owner to reassess the product backlog priorities based on user feedback

    B.

    Continue with the planned features since they meet the technical requirements

    C.

    Facilitate sessions with users and stakeholders to better understand what would deliver real value

    D.

    Increase the team's velocity to deliver more features in the next iteration

    E.

    Focus on improving the technical quality of the delivered features

    F.

    Document the user feedback for consideration in future projects

    How to approach this question

    Focus on actions that address the value delivery issue by reassessing priorities and engaging with users to understand their real needs.

    Full Answer

    A,C
    When delivered features don't provide expected value, reassessing priorities (A) and engaging users to understand real needs (C) addresses the root issue.

    Common mistakes

    Focusing on delivery efficiency or technical quality instead of addressing the fundamental value delivery problem.
    Question 27All questionsQuestion 29

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →