Hard1 markMultiple Choice
Task 13: Mentor relevant stakeholdersservant leadershipindividual coachingtime managementteam member support
PMP · Question 29 · Task 13: Mentor relevant stakeholders
A project manager is leading a team where one member consistently produces high-quality work but struggles with time management and frequently misses deadlines. The team member seems overwhelmed but hasn't asked for help. What should the project manager do FIRST?
A project manager is leading a team where one member consistently produces high-quality work but struggles with time management and frequently misses deadlines. The team member seems overwhelmed but hasn't asked for help. What should the project manager do FIRST?
Answer options:
A.
Have a private coaching conversation to understand the challenges and explore solutions together
B.
Assign a mentor from the team to help with time management skills
C.
Reduce the team member's workload to match their current capacity
D.
Provide time management training resources and tools
How to approach this question
Servant leadership prioritizes understanding the individual's situation and collaboratively finding solutions rather than imposing generic fixes.
Full Answer
A.Have a private coaching conversation to understand the challenges and explore solutions together✓ Correct
Servant leaders focus on understanding individual challenges and collaboratively developing solutions that address root causes rather than symptoms.
Common mistakes
Imposing solutions without understanding the specific challenges, or treating all time management issues as generic problems requiring standard solutions.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard