    PracticePMI PMP®PMI PMP Practice Exam 3Question 30
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodology/methods and practiceshybrid methodologycompliance documentationagile practicesregulatory requirements

    PMP · Question 30 · Task 13: Determine appropriate project methodology/methods and practices

    A project manager is working on a software development project where the client wants to see progress every two weeks but also needs comprehensive documentation for regulatory compliance. The development team prefers agile practices but the compliance requirements suggest more predictive documentation. What approach should the project manager recommend?

    Answer options:

    A.

    Use pure agile methodology and create documentation at the end of the project

    B.

    Use predictive methodology with detailed upfront documentation and bi-weekly status reports

    C.

    Use a hybrid approach with agile development practices and concurrent documentation processes

    D.

    Alternate between agile and predictive approaches for different project phases

    How to approach this question

    When projects have competing needs (agile delivery + compliance documentation), look for hybrid approaches that address both requirements simultaneously.

    Full Answer

    C.Use a hybrid approach with agile development practices and concurrent documentation processes✓ Correct
    Hybrid approaches allow projects to combine the benefits of different methodologies to address multiple, sometimes competing, project requirements.

    Common mistakes

    Trying to use pure methodologies when project requirements clearly indicate the need for hybrid approaches that combine different elements.
    Question 29All questionsQuestion 31

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →