PMP · Question 41 · Task 2: Manage communications
A project manager is leading an agile project where the product owner frequently changes priorities between sprints, causing the development team to feel frustrated and questioning the value of their completed work. What should the project manager do FIRST?
Answer options:
Ask the product owner to commit to priorities for at least three sprints to provide stability
Explain to the development team that changing priorities are normal in agile projects
Facilitate a discussion between the product owner and development team to improve understanding of priority changes
Implement a change control process for backlog priority modifications
100 questions · hints · full answers · grading