    Task 3: Assess and manage risksclient consultationrisk communicationinformed decision makingcomplexity assessment

    PMP · Question 60 · Task 3: Assess and manage risks

    A project manager is leading a software development project where the client has requested a feature that would require integration with a legacy system. The integration is possible but would significantly increase project complexity and risk. The feature would provide moderate business value. What should the project manager do?

    Answer options:

    A.

    Recommend against the feature due to the complexity and risk it introduces

    B.

    Present the client with a clear analysis of the complexity, risks, costs, and benefits to enable an informed decision

    C.

    Implement the feature as requested since the client is paying for the project

    D.

    Propose alternative approaches that might provide similar business value with less complexity

    How to approach this question

    When clients request features with significant complexity or risk, provide complete information to enable informed business decisions rather than making the decision for them.

    Full Answer

    B.Present the client with a clear analysis of the complexity, risks, costs, and benefits to enable an informed decision✓ Correct
    B
    Project managers should provide clients with complete information about complexity, risks, costs, and benefits so they can make informed business decisions.

    Common mistakes

    Either making the decision for the client or implementing requests without ensuring the client understands the full implications.
    Question 59All questionsQuestion 61

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →