PMP · Question 75 · Task 6: Plan and manage schedule
A project manager is working on an agile project where the product owner has been making priority decisions without consulting the development team about technical dependencies and effort implications. This has led to inefficient sprint planning and frustrated developers. What should the project manager do?
A project manager is working on an agile project where the product owner has been making priority decisions without consulting the development team about technical dependencies and effort implications. This has led to inefficient sprint planning and frustrated developers. What should the project manager do?
Answer options:
Facilitate collaborative planning sessions where the product owner and development team can share perspectives on priorities and technical considerations
Require the product owner to consult with the development team before making any priority changes
Give the development team veto power over product owner priority decisions
Create a technical review board to evaluate all product owner decisions
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
Expert