    PracticePMI PMP®PMI PMP Practice Exam 3Question 75
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleproduct owner collaborationsprint planningtechnical dependenciescollaborative planning

    PMP · Question 75 · Task 6: Plan and manage schedule

    A project manager is working on an agile project where the product owner has been making priority decisions without consulting the development team about technical dependencies and effort implications. This has led to inefficient sprint planning and frustrated developers. What should the project manager do?

    Answer options:

    A.

    Facilitate collaborative planning sessions where the product owner and development team can share perspectives on priorities and technical considerations

    B.

    Require the product owner to consult with the development team before making any priority changes

    C.

    Give the development team veto power over product owner priority decisions

    D.

    Create a technical review board to evaluate all product owner decisions

    How to approach this question

    When product owners and development teams aren't collaborating effectively, facilitate processes that bring their perspectives together rather than creating rigid rules or hierarchies.

    Full Answer

    A.Facilitate collaborative planning sessions where the product owner and development team can share perspectives on priorities and technical considerations✓ Correct
    Effective agile planning requires collaboration between business knowledge (product owner) and technical expertise (development team) to make informed priority decisions.

    Common mistakes

    Creating rigid processes or power structures instead of facilitating ongoing collaboration between business and technical perspectives.
    Question 74All questionsQuestion 76

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →