PMP · Question 84 · Task 4: Engage stakeholders
A project manager is working with a team that has been using agile practices successfully, but a new senior stakeholder has joined who insists on detailed upfront planning and comprehensive documentation. The stakeholder threatens to withdraw support if these requirements aren't met. What should the project manager do?
Answer options:
Switch to a predictive methodology to satisfy the stakeholder's requirements
Work with the stakeholder to understand their underlying concerns and explore how agile practices can address those needs
Explain to the stakeholder why agile practices are superior to traditional planning approaches
Escalate the conflict to senior management for resolution
100 questions · hints · full answers · grading