PMP · Question 89 · Task 8: Plan and manage scope
A project manager is working on a software development project where the client has requested integration with a legacy system that has poor documentation and limited technical support. The integration is possible but would significantly increase project complexity and maintenance burden. What should the project manager do?
A project manager is working on a software development project where the client has requested integration with a legacy system that has poor documentation and limited technical support. The integration is possible but would significantly increase project complexity and maintenance burden. What should the project manager do?
Answer options:
Present the client with a detailed analysis of integration complexity, long-term maintenance implications, and alternative approaches
Recommend against the legacy integration due to complexity and maintenance concerns
Implement the integration as requested since the client understands their business needs
Propose building a modern replacement for the legacy system instead of integrating with it
How to approach this question
Full Answer
Common mistakes