    PracticePMI PMP®PMI PMP Practice Exam 4Question 07
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamimpediment removalservant leadershipvendor managementproblem solving

    PMP · Question 07 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    During a sprint planning session, the development team identifies that they cannot proceed with three high-priority user stories because the required API documentation from a third-party vendor is incomplete and the vendor's technical team is unresponsive. This impediment affects 40% of the planned sprint work and could impact the upcoming release. What should the project manager do FIRST?

    Answer options:

    A.

    Escalate to senior management to apply pressure on the vendor relationship

    B.

    Immediately contact the vendor through multiple channels and leverage professional networks to establish communication with their technical team

    C.

    Replan the sprint to focus on other user stories while waiting for the vendor response

    D.

    Document the impediment in the risk register and continue with sprint planning

    How to approach this question

    Look for active impediment removal approaches that leverage networks and resources before escalating or working around the problem.

    Full Answer

    B.Immediately contact the vendor through multiple channels and leverage professional networks to establish communication with their technical team✓ Correct
    B
    Servant leaders actively work to remove impediments using their networks and resources, taking immediate action to unblock teams rather than simply documenting or working around problems.

    Common mistakes

    Students often choose escalation or workaround approaches rather than recognizing the servant leader's role in actively removing impediments.
    Question 06All questionsQuestion 08

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard