    PracticePMI PMP®PMI PMP Practice Exam 4Question 11
    Hard1 markMultiple Choice
    Task 11: Engage and support virtual teamsvirtual teamsdistributed teamsteam engagementtime zones

    PMP · Question 11 · Task 11: Engage and support virtual teams

    A project team is distributed across four countries with significant time zone differences (12-hour spread). Team members report feeling isolated, missing important decisions made during their off-hours, and struggling to maintain team cohesion. The project requires close collaboration and frequent decision-making. What should the project manager do FIRST?

    Answer options:

    A.

    Establish core working hours that overlap across all time zones for daily collaboration

    B.

    Implement a follow-the-sun model where work is passed between time zones continuously

    C.

    Increase the frequency of status reports and documentation to keep everyone informed

    D.

    Assess individual team member needs and constraints to design a customized engagement approach for the distributed environment

    How to approach this question

    Look for approaches that assess individual needs and constraints before designing solutions for distributed team challenges.

    Full Answer

    D.Assess individual team member needs and constraints to design a customized engagement approach for the distributed environment✓ Correct
    D
    Effective virtual team engagement requires understanding individual team member needs, constraints, and preferences to design customized approaches that work for the specific distributed environment.

    Common mistakes

    Students often choose generic solutions rather than recognizing the need to assess individual needs first when designing distributed team engagement strategies.
    Question 10All questionsQuestion 12

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard