    PracticePMI PMP®PMI PMP Practice Exam 4Question 21
    Hard1 markMultiple Choice
    Task 7: Plan and manage quality of products/deliverablesquality managementdefinition of donecustomer satisfactionquality standards

    PMP · Question 21 · Task 7: Plan and manage quality of products/deliverables

    A software development team is consistently delivering features that meet functional requirements but are experiencing increasing customer complaints about usability and performance. The team follows a definition of done that includes code review, unit testing, and functional testing, but customer satisfaction scores are declining. What should the project manager do FIRST?

    Answer options:

    A.

    Add more rigorous testing phases to the development process

    B.

    Implement customer feedback sessions after each release to identify issues

    C.

    Collaborate with stakeholders to expand the definition of done to include usability and performance criteria

    D.

    Assign dedicated resources to focus on usability and performance optimization

    How to approach this question

    Look for approaches that address the root cause by aligning quality standards with customer expectations and business value.

    Full Answer

    C.Collaborate with stakeholders to expand the definition of done to include usability and performance criteria✓ Correct
    Effective quality management requires aligning quality standards with customer expectations and business value, not just technical functionality.

    Common mistakes

    Students often choose testing or resource approaches rather than recognizing the need to align quality standards with customer value.
    Question 20All questionsQuestion 22

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard