Hard1 markMultiple Choice
Task 9: Integrate project planning activitiesproject integrationdependency analysiscritical pathworkstream coordination

PMP · Question 23 · Task 9: Integrate project planning activities

A project manager is integrating plans from multiple workstreams for a large organizational transformation. The technical implementation plan shows completion in 8 months, the change management plan requires 12 months, the training plan needs 6 months, and the data migration plan estimates 10 months. Each plan was developed independently and there are potential dependencies between workstreams. What should the project manager do FIRST?

Answer options:

A.

Set the overall project timeline to 12 months based on the longest individual plan

B.

Ask each workstream to compress their timelines to align with the shortest plan

C.

Analyze dependencies and integration points between workstreams to identify the critical path and optimal sequencing

D.

Create a master schedule that runs all workstreams in parallel to minimize overall duration

How to approach this question

Look for systematic approaches that analyze dependencies and integration points before determining overall project timing.

Full Answer

C.Analyze dependencies and integration points between workstreams to identify the critical path and optimal sequencing✓ Correct
C
Effective project integration requires analyzing dependencies and integration points between workstreams to determine optimal sequencing and realistic timelines.

Common mistakes

Students often choose simple timeline approaches rather than recognizing the need to analyze dependencies and integration points.

Practice the full PMI PMP Practice Exam 4

90 questions · hints · full answers · grading

More questions from this exam