PMP · Question 24 · Task 10: Manage project changes
During the execution of a predictive project, a major supplier announces they are discontinuing a key component that represents 15% of the project deliverable. Alternative suppliers exist but would require significant design changes and a 6-week delay. The current project timeline has only 2 weeks of buffer remaining. What should the project manager do FIRST?
During the execution of a predictive project, a major supplier announces they are discontinuing a key component that represents 15% of the project deliverable. Alternative suppliers exist but would require significant design changes and a 6-week delay. The current project timeline has only 2 weeks of buffer remaining. What should the project manager do FIRST?
Answer options:
Immediately implement the design changes and inform stakeholders of the 6-week delay
Assess the impact of various response options and prepare a change request with recommendations for stakeholder decision
Negotiate with the supplier to continue providing the component until project completion
Remove the affected component from the project scope to avoid delays
How to approach this question
Full Answer
Common mistakes