Task 10: Manage project changeschange managementsupplier issuesimpact assessmentgovernance

PMP · Question 24 · Task 10: Manage project changes

During the execution of a predictive project, a major supplier announces they are discontinuing a key component that represents 15% of the project deliverable. Alternative suppliers exist but would require significant design changes and a 6-week delay. The current project timeline has only 2 weeks of buffer remaining. What should the project manager do FIRST?

Answer options:

A.

Immediately implement the design changes and inform stakeholders of the 6-week delay

B.

Assess the impact of various response options and prepare a change request with recommendations for stakeholder decision

C.

Negotiate with the supplier to continue providing the component until project completion

D.

Remove the affected component from the project scope to avoid delays

How to approach this question

Look for change management approaches that analyze options and provide stakeholders with information for informed decision-making.

Full Answer

B.Assess the impact of various response options and prepare a change request with recommendations for stakeholder decision✓ Correct
B
Effective change management requires analyzing response options, assessing impacts, and providing stakeholders with recommendations through proper governance processes.

Common mistakes

Students often choose immediate action approaches rather than recognizing the need to follow change management processes and provide stakeholder options.

Practice the full PMI PMP Practice Exam 4