PMP · Question 33 · Task 2: Evaluate and deliver project benefits and value
A project manager has completed a customer relationship management (CRM) system implementation. The system is functioning as designed and meets all technical requirements. However, six months after go-live, user adoption is lower than expected, and the anticipated business benefits of improved customer retention and sales efficiency have not materialized. What should the project manager do FIRST?
A project manager has completed a customer relationship management (CRM) system implementation. The system is functioning as designed and meets all technical requirements. However, six months after go-live, user adoption is lower than expected, and the anticipated business benefits of improved customer retention and sales efficiency have not materialized. What should the project manager do FIRST?
Answer options:
Provide additional user training to increase system adoption rates
Enhance the system features to make it more user-friendly and valuable
Conduct a benefits realization assessment to identify barriers to value achievement and user adoption
Extend the benefits measurement period since organizational change takes time
How to approach this question
Full Answer
Common mistakes