PMP · Question 39 · Task 4: Empower team members and stakeholders
A project manager wants to empower a mature agile team to make more autonomous decisions about their work processes and technical approaches. The team has demonstrated strong collaboration and delivery capabilities over the past year. Which TWO actions should the project manager take to effectively empower the team?
A project manager wants to empower a mature agile team to make more autonomous decisions about their work processes and technical approaches. The team has demonstrated strong collaboration and delivery capabilities over the past year. Which TWO actions should the project manager take to effectively empower the team?
Answer options:
Remove all oversight and let the team operate completely independently
Define clear boundaries and constraints within which the team can make autonomous decisions
Create detailed procedures for all decisions the team is authorized to make
Require the team to document all decisions for management review
Assign decision-making authority only for low-risk, routine decisions
Establish regular check-ins to provide support and guidance when needed
How to approach this question
Full Answer
Common mistakes