For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 42
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamimpediment removalservant leadershipcollaborationproblem solving

    PMP · Question 42 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    A development team reports that they cannot complete their sprint commitment because the database administrator (DBA) team has not provided the required database schema changes. The DBA team says they are waiting for security approval, which typically takes 2-3 weeks. This impediment affects multiple user stories and could impact the release timeline. What should the project manager do FIRST?

    Answer options:

    A.

    Escalate to senior management to expedite the security approval process

    B.

    Work with both teams to identify alternative approaches or workarounds that don't require the security approval

    C.

    Adjust the sprint plan to focus on user stories that don't require database changes

    D.

    Document the impediment in the risk register and continue with the current plan

    How to approach this question

    Look for active impediment removal approaches that work with teams to find solutions rather than escalating or working around the problem.

    Full Answer

    B.Work with both teams to identify alternative approaches or workarounds that don't require the security approval✓ Correct
    B
    Servant leaders actively work to remove impediments by collaborating with affected teams to identify alternatives and solutions rather than simply escalating or working around problems.

    Common mistakes

    Students often choose escalation or workaround approaches rather than recognizing the servant leader's role in actively removing impediments through collaboration.
    Question 41All questionsQuestion 43

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →