Hard1 markShort Answer
PMP · Question 43 · Task 6: Plan and manage schedule
A project has the following earned value metrics at month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Earned Value (EV): $720,000<br/>- Actual Cost (AC): $800,000<br/>- Planned Value (PV): $840,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only (e.g., 0.86).
A project has the following earned value metrics at month 10:<br/>- Budget at Completion (BAC): $1,200,000<br/>- Earned Value (EV): $720,000<br/>- Actual Cost (AC): $800,000<br/>- Planned Value (PV): $840,000<br/><br/>Calculate the Schedule Performance Index (SPI). Round to two decimal places and enter numbers only (e.g., 0.86).
How to approach this question
Calculate SPI using the formula: SPI = EV / PV. Divide Earned Value by Planned Value and round to two decimal places.
Full Answer
0.86
Schedule Performance Index (SPI) measures schedule efficiency by comparing earned value to planned value. An SPI of 0.86 indicates the project is behind schedule, accomplishing only 86% of the planned work.
Common mistakes
Students sometimes confuse SPI with CPI formulas or use AC instead of PV in the calculation.
Practice the full PMI PMP Practice Exam 4
90 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
Expert