Hard1 markMultiple Choice
Task 7: Plan and manage quality of products/deliverablesquality managementdefinition of donecustomer satisfactionquality standards

PMP · Question 57 · Task 7: Plan and manage quality of products/deliverables

A software development team has been consistently delivering features that meet functional requirements, but customer feedback indicates issues with usability, performance, and accessibility. The team's Definition of Done includes code review, unit testing, and functional testing, but customer satisfaction scores are declining despite meeting all technical criteria. What should the project manager do FIRST?

Answer options:

A.

Add performance testing and usability testing to the existing testing processes

B.

Implement customer feedback sessions after each release to identify issues

C.

Collaborate with stakeholders to expand the Definition of Done to include usability, performance, and accessibility criteria

D.

Create a separate quality assurance team focused on usability and performance

How to approach this question

Look for approaches that address the root cause by expanding quality standards to include customer-focused criteria.

Full Answer

C.Collaborate with stakeholders to expand the Definition of Done to include usability, performance, and accessibility criteria✓ Correct
C
Effective quality management requires aligning quality standards with customer expectations and business value, not just technical functionality.

Common mistakes

Students often choose testing or resource approaches rather than recognizing the need to align quality standards with customer value.