For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 59
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesproject integrationdependency analysiscritical pathprogram management

    PMP · Question 59 · Task 9: Integrate project planning activities

    A project manager is integrating plans from multiple workstreams for a large digital transformation program. The technical workstream estimates 10 months, the change management workstream requires 14 months, the training workstream needs 8 months, and the data migration workstream estimates 12 months. Each plan was developed independently, and there are significant dependencies between workstreams that haven't been fully analyzed. What should the project manager do FIRST?

    Answer options:

    A.

    Set the overall program timeline to 14 months based on the longest individual workstream

    B.

    Ask each workstream to compress their timelines to align with the shortest plan

    C.

    Conduct dependency analysis and integration mapping to identify the critical path and optimal workstream sequencing

    D.

    Run all workstreams in parallel to minimize overall program duration

    How to approach this question

    Look for systematic approaches that analyze dependencies and integration points before determining overall program timing and sequencing.

    Full Answer

    C.Conduct dependency analysis and integration mapping to identify the critical path and optimal workstream sequencing✓ Correct
    Effective project integration requires analyzing dependencies and integration points between workstreams to determine optimal sequencing and realistic timelines for the overall program.

    Common mistakes

    Students often choose simple timeline approaches rather than recognizing the need to analyze dependencies and integration points first.
    Question 58All questionsQuestion 60

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →