Hard1 markMultiple Choice
Task 9: Integrate project planning activitiesproject integrationdependency analysiscritical pathprogram management

PMP · Question 59 · Task 9: Integrate project planning activities

A project manager is integrating plans from multiple workstreams for a large digital transformation program. The technical workstream estimates 10 months, the change management workstream requires 14 months, the training workstream needs 8 months, and the data migration workstream estimates 12 months. Each plan was developed independently, and there are significant dependencies between workstreams that haven't been fully analyzed. What should the project manager do FIRST?

Answer options:

A.

Set the overall program timeline to 14 months based on the longest individual workstream

B.

Ask each workstream to compress their timelines to align with the shortest plan

C.

Conduct dependency analysis and integration mapping to identify the critical path and optimal workstream sequencing

D.

Run all workstreams in parallel to minimize overall program duration

How to approach this question

Look for systematic approaches that analyze dependencies and integration points before determining overall program timing and sequencing.

Full Answer

C.Conduct dependency analysis and integration mapping to identify the critical path and optimal workstream sequencing✓ Correct
C
Effective project integration requires analyzing dependencies and integration points between workstreams to determine optimal sequencing and realistic timelines for the overall program.

Common mistakes

Students often choose simple timeline approaches rather than recognizing the need to analyze dependencies and integration points first.