PMP · Question 63 · Task 13: Determine appropriate project methodology/methods and practices
A project manager is assigned to lead a new mobile application development project. The business requirements are well-defined and stable, but the organization wants to incorporate user feedback throughout development and deliver working features every 4 weeks. The development team has experience with both waterfall and agile approaches. The application must comply with strict data privacy regulations before final release. What methodology should the project manager recommend?
Answer options:
Pure Agile methodology to support iterative delivery and continuous user feedback
Waterfall methodology since requirements are stable and well-defined
Hybrid methodology combining predictive planning with iterative delivery and continuous feedback loops
Iterative methodology with multiple development cycles and user validation points